Nuclear Case (Article) Nuclear Case (Graphics) Energy Options Business Climate
The Data Center Reality

$156 Billion in Projects
Blocked or Stalled

Data centers power your 911 calls, bank transactions, medical records, and weather forecasts. They are not just for AI. But 533+ moratoriums across 42 states are blocking the infrastructure America runs on. Project cancellations jumped from 6 in 2024 to 25 in 2025, with 20+ more in early 2026 alone. China builds without pause.

$156B
Cumulative projects blocked/stalled (2024-2026)
533+
Local moratoriums across 42 states
833
Active opposition groups (up from 396 in late 2025)
42
Specific projects tracked on this page
$926B
Data center GDP contribution (2024)
70%
Of Americans oppose local data centers (Gallup, Mar 2026)

Interactive Map: Where Data Centers Are Being Stopped

Click any pin to see the project details, developer, investment value, and what blocked it. Red = cancelled/rejected. Orange = moratorium. Purple = blocked/litigation. Cyan = withdrawn by developer.

ProjectLocationDeveloperInvestmentStatusDate

15 Arguments Against Data Centers, Answered

Every major opposition talking point, the organizations behind it, and the data that tells the full story. Click any claim to see the rebuttal.

Project Taurus: What the Opposition Claims vs. What the Data Shows

Raeden's proposed 50 MW data center at a former Intel semiconductor plant on High Tech Way was heard by City Council on September 17, 2026. After 126 speakers opposed and 22 spoke in favor at a heated special session at the Pikes Peak Center, the Council voted 7-2 to postpone the final decision to April 13, 2027. The Planning Commission had previously voted 6-2 to approve after a 14-hour hearing. Here is every major claim, and what the evidence actually supports.

50 MW
IT load capacity
$1B
Projected investment
$950M
Tax revenue over 20 years
$0
Tax incentives requested
80-100
Permanent jobs
Apr 13
Postponed Council vote (2027)
🔊
Will it be too noisy?
What opponents claim

The 36 air-cooled chillers and 30 backup generators will produce 24/7 noise that "dismantles wellbeing." Residents report concerns about infrasound, low-frequency vibration, and the "constant hum" remembered from when Intel operated the facility. The site directly abuts the Chelsea Glen residential neighborhood.

What the data shows

Raeden projects noise at 49 dBA at the property line, equivalent to a quiet suburban neighborhood at night. They added a 30-foot sound wall, relocated backup generators away from Chelsea Glen, added noise-limiting enclosures around chillers, and posted a $1 million remediation bond. The site is zoned industrial and previously housed a semiconductor fab.

Assessment

Concern is legitimate but has been addressed. The 49 dBA projection is below residential noise limits in most jurisdictions. The sound wall, equipment relocation, and $1M bond are meaningful commitments. The Planning Commission capped operations at 50 MW; exceeding it requires a new public hearing. The site was industrial before and is zoned industrial. The real question is whether the 49 dBA projection holds at full capacity. Requiring independent third-party noise monitoring as a permit condition would settle this definitively.

🎵
What about low-frequency noise and infrasound?
What opponents claim

Residents report a constant low-frequency hum from data center cooling systems that standard noise meters fail to capture. Standard dBA measurements underweight low frequencies, meaning a facility can be "in compliance" while residents experience dizziness, nausea, sleep disruption, and chronic headaches. Opponents cite the WHO's 1999 conclusion that A-weighting "underestimates the sound pressure level of noise with low-frequency components." Six class-action noise lawsuits were filed against data centers in 2026 alone, including against Microsoft's Sturtevant, WI facility.

What the data shows

The low-frequency noise debate mirrors the "wind turbine syndrome" claims that were extensively studied and debunked by the WHO, U.S. DOE, and multiple health agencies. A landmark 2014 University of Auckland study found people reported identical symptoms from sham infrasound (silence) as from real infrasound when primed with health warnings, demonstrating the nocebo effect. A 2026 MDPI review found no published study has measured harmful LFN levels at an operational data center using appropriate instrumentation. The JLARC Virginia study measured 40-59 dBA at property lines, falling within normal suburban ambient levels. The most comprehensive systematic review (Baliatsas et al., 2016) found only 7 qualifying studies, all with "moderate" quality at best, concluding evidence for health effects beyond annoyance is "limited and inconclusive." No data center noise nuisance lawsuit has reached summary judgment or trial.

Assessment

This is a solvable engineering problem, not an inherent threat. The low-frequency noise argument follows the same pattern as "wind turbine syndrome": genuine perception amplified by expectation bias into claimed health effects that controlled studies do not support. For Project Taurus specifically, the site previously housed an Intel semiconductor fab that operated 24/7 with industrial HVAC and cleanroom systems generating comparable low-frequency profiles. Raeden targets 43 dBA at the property line (below typical suburban ambient of 45-50 dBA), verified by two independent city-commissioned studies. Mitigations include 30-42 foot sound-attenuating walls, fully enclosed chillers and generators, and a $1 million remediation bond with an evergreen clause (the first of its kind nationally). The Planning Commission already added dBC monitoring as a permit condition to specifically capture low-frequency noise, closing the measurement gap opponents cite. This goes beyond what almost any jurisdiction in the country requires.

💧
Will it drain Colorado Springs' water?
What opponents claim

EESI reports large AI data centers can use up to 5 million gallons of water per day. Colorado Springs faces drought risk. Adding any large industrial water consumer is irresponsible. Opponents question whether closed-loop claims are credible.

What the data shows

Raeden uses a closed-loop air-cooled system requiring a one-time fill of approximately 200,000 gallons that is never exposed to air and never evaporates. This is not an evaporative cooling tower. The 5 million gallon/day figure opponents cite applies to water-cooled facilities, which this is not. Air-cooled systems use orders of magnitude less water.

Assessment

This concern does not hold up against the project's actual design. The opposition is citing industry-wide water figures for evaporative cooling systems and applying them to a closed-loop air-cooled facility. These are fundamentally different technologies. A 200,000-gallon one-time fill is roughly the equivalent of filling 6 residential swimming pools. Colorado Springs Utilities has stated it can serve the project. The water argument is the weakest of the opposition claims for this specific project.

⚡
Will it raise electricity bills for residents?
What opponents claim

50 MW equals the power demand of 30,000-50,000 homes. CSU has received 10 data center requests totaling 1,420 MW, roughly equal to its entire generating capacity. Opponents argue "everyone on the grid" will pay. CSU faces coal plant closure deadlines that complicate adding massive new loads.

What the data shows

Colorado Springs Utilities has a large-load tariff that requires Raeden to: (1) sign a 10-year contract, (2) provide 36 months of financial collateral, (3) pay for all power infrastructure upgrades, and (4) pay for reserved capacity even if unused. CSU's General Manager stated rates will not increase for homeowners as a result of this project.

Assessment

This concern does not hold up for Project Taurus. The large-load tariff is the right policy mechanism. Raeden pays for its own infrastructure, its own capacity, and bears the financial risk. Special rates have been agreed to specifically to ensure residential ratepayers do not bear the burden of increased power costs. Beyond protection, Raeden purchasing power off the grid actually benefits Colorado Springs by strengthening the city's base load and improving its overall buying power with energy suppliers. CSU's General Manager has confirmed rates will not increase for homeowners as a result of this project.

☣
What about PFAS and diesel generators?
What opponents claim

GreenLatinos' Ean Tafoya raised PFAS ("forever chemicals"), ethylene glycol, and hydrofluorocarbon concerns. Colorado Springs communities (Fountain, Security, Widefield) already suffer PFAS drinking water contamination. The 30 diesel backup generators emit PM2.5 and NOx. Opponents want a full air quality impact analysis.

What the data shows

Raeden states generators are fitted with Selective Catalytic Reduction (SCR) systems and run only 20-30 minutes per month for testing. PFAS use in closed-loop cooling systems does not involve discharge to the environment. The PFAS contamination in Fountain/Security came from military fire-fighting foam (AFFF) at Peterson AFB, not from industrial cooling. These are different chemicals in different applications.

Assessment

PFAS concern is understandable given local history, but misapplied to this project. The Fountain/Security/Widefield contamination came from AFFF foam, not industrial cooling. Closed-loop cooling does not discharge chemicals. The diesel generator concern is more legitimate, especially for a community with ozone issues. Requiring a full air quality assessment and phasing in battery backup to replace diesel over time would be reasonable conditions.

🔍
Was the approval process transparent?
What opponents claim

The city violated its own Unified Development Code by granting administrative approval for a major modification without public hearing. Raeden introduced multiple plan versions after staff approval. The actual AI tenant is undisclosed (Raeden cites NDAs). Opponents allege the city approved 100 MW capacity, not the 50 MW publicly promoted. Integrity Matters filed a 200-page appeal citing seven grounds for reversal.

What the data shows

The Planning Commission heard all five appeals over a 14-hour session and voted 6-2 to uphold the approval. The site is zoned industrial and previously operated as a semiconductor fab. The commission capped utility use at 50 MW with a requirement to return for public review if exceeded. NDAs between developers and tenants are standard industry practice. On September 17, City Council heard 126 speakers against and 22 in favor, then voted 7-2 to postpone the final decision to April 13, 2027.

Assessment

This concern misrepresents what actually happened. Raeden purchased an existing building in an industrial area already zoned for this type of work. The project requires less water than the site is already allocated. Under the city's development code, this project could have been approved purely through administrative review with no public process required at all. The city and the vendor voluntarily chose to provide an extraordinary level of transparency when none was legally necessary. The Planning Commission held a 14-hour public hearing, voted 6-2 to uphold the approval, and capped utility use at 50 MW with a requirement to return for public review if exceeded. Rather than evidence of a flawed process, this is a case where the city went far above and beyond its obligations to engage the community.

Overall assessment: Project Taurus

The project's substantive risks have been addressed. The process was more transparent than required.

Water: Not a real issue for this project. Closed-loop air-cooled system. 200,000-gallon one-time fill. The opposition is applying evaporative cooling data to a non-evaporative design.

Noise: Addressed through the 30-foot sound wall, equipment relocation, and $1M remediation bond. The 49 dBA projection is reasonable for an industrial zone. Independent monitoring should be a permit condition.

Electricity rates: Protected by CSU's large-load tariff with special rates agreed to ensure residents are not burdened. Raeden pays for all infrastructure, provides 36 months of collateral, and pays for reserved capacity even if unused. Purchasing power off the grid strengthens Colorado Springs' base load and improves the city's buying power. CSU confirmed residential rates will not increase.

Environment: PFAS concern is misapplied (different chemicals, different applications from the Fountain/Security contamination). Diesel generators are a legitimate concern that should transition to battery backup over time.

Process: Raeden purchased a building in an industrial zone already approved for this type of use and requires less water than the site is allocated. Administrative approval was all that was legally required. The city and vendor voluntarily provided extraordinary public transparency, including a 14-hour Planning Commission hearing, when none was necessary. This was a strength, not a weakness.

The project is a $1 billion investment requesting zero tax incentives on a site that is already zoned industrial, previously housed a semiconductor fab, and has existing power and infrastructure. It generates an estimated $950 million in tax revenue over 20 years and creates 80-100 permanent jobs. The opposition's arguments do not hold up against the project's actual details, design, and agreed-upon terms.

Not Just AI. Everything You Rely On.

When you call 911, check your bank balance, file taxes, get an MRI, or check the weather, you are using a data center. The opposition frames this as a tech industry fight. It is not. It is the infrastructure of modern life.

🚑
911 & Emergency Services
Next Generation 911 (NG911) runs on cloud infrastructure. Without data centers, emergency dispatch cannot scale during natural disasters.
🏥
Healthcare
Electronic health records, telemedicine, medical imaging (CT, MRI, X-ray), drug discovery, and clinical research. A midsized hospital generates 55+ petabytes/year.
🏦
Banking & Finance
Every credit card swipe, wire transfer, ATM withdrawal, mobile banking session, and real-time fraud detection on billions of daily transactions.
🏛
Government Services
Social Security payments for 70M+ beneficiaries. IRS processing 150M+ tax returns. DMV, passports, immigration, census, elections, and veterans' benefits.
🎓
Education
Google Classroom, Microsoft Teams, university research computing, online learning platforms (Coursera, Khan Academy), student records, and school systems.
💼
Small Business
Cloud computing (AWS, Azure), email, websites, point-of-sale systems (Square, Toast), payroll (QuickBooks, ADP), and e-commerce (Shopify). Every small business uses data centers.
🌾
Agriculture
Precision farming sensors, drone data processing, satellite imagery, weather analytics, soil monitoring, commodity trading, and farm management software.
🛡
Military & National Security
Intelligence processing, satellite data, drone operations, command and control. Defense AI data center market: $12.5B growing to $64B by 2033. Designated "critical defense facilities."
🌡
Weather & Climate
NOAA weather models, hurricane tracking, severe weather warnings, climate research. The forecasts that save lives run on data center compute.
🚚
Transportation
GPS navigation, ride-sharing (Uber/Lyft), airline booking systems, air traffic control, traffic management, and autonomous vehicle data processing.
🎬
Entertainment
Netflix, Spotify, gaming, social media. Streaming alone accounts for a significant share of internet traffic, all served from data centers.
📚
E-Commerce
Every online purchase, from Amazon to a local shop's Shopify store, is processed through data center infrastructure. $1.1 trillion in US e-commerce (2024).
What data centers contributed in 2024

$926.9 billion in GDP (up 21% from $768B in 2023). 5.5 million jobs supported (up 17%). $204.4 billion in tax contributions (up 24%). Without data center investment, U.S. GDP growth in H1 2025 would have been just 0.1%. Data centers drove roughly 92% of GDP growth that period.

Before Data Centers, Every Company Ran Its Own Server Room

Saying no to data centers does not reduce computing demand. It pushes that demand into thousands of smaller, older, less efficient server rooms in every office building, hospital, and government agency. The result is more energy waste, more cooling water, weaker security, and higher costs per unit of computing.

MetricEnterprise Server RoomModern Hyperscale Data CenterImprovement
Power Usage Effectiveness (PUE)1.5 - 1.8+1.09 - 1.2030-50% less energy waste
Server utilization5% - 15%40% - 60%+4-12x more compute per server
Computing work per wattBaseline3-5x more3-5x more efficient
Physical securityLocked door, maybe a camera24/7 staff, mantraps, biometricsEnterprise-grade
Uptime guaranteeVariable, no redundancy99.995% (Tier 4 = 26 min/yr)Near-perfect
Power redundancyNone to basic UPSN+1 to 2N+1No single point of failure
Cooling efficiencyBasic AC, often inadequateLiquid/zero-water systems90% less water possible
Compliance (HIPAA, PCI, SOC)Ad hocFull regulatory complianceRequired for healthcare, banking
Clean energy commitmentNone72% of all green PPAs signed by DCsLargest clean energy buyers on Earth
The bottom line

Google's fleet-wide PUE of 1.09 means for every watt of computing, only 0.09 watts go to overhead. In a typical enterprise server room, that overhead is 0.5-1.0+ watts. Data center developers signed 72% of all green energy power purchase agreements (PPAs) in 2025 and contracted 50 GW of clean energy by Q3 2024. No other sector is investing more in new clean generation. Blocking data centers does not make computing greener. It makes it dirtier.

Who Is Really Behind the Opposition?

Many local groups are genuinely grassroots. But the national movement blocking $156+ billion in projects is coordinated by professional advocacy organizations with $20M+ budgets, funded by the same progressive foundation network that ran the anti-fracking and anti-pipeline campaigns. The Arabella Advisors network (rebranded as Vital Impact in 2025) has funneled over $500 million in foreign and dark money through pass-through foundations. The playbook, the funders, and in some cases the people are identical.

The Central Coordinator
Food & Water Watch
$20.8M
Annual revenue (FY2025)
520+
Orgs in their coalition (48 states)
9+
Professional toolkits distributed
Same
Funders as anti-fracking movement

Washington D.C.-based Food & Water Watch (founded by Wenonah Hauter, $226K compensation) runs the national "Stop Data Centers Coalition." They published "Top 10 Reasons Data Centers Must Be Stopped," distribute the "How to Stop a Data Center Near You" organizing guide, coordinated the 520-organization moratorium letter, and supported the Sanders-AOC AI Data Center Moratorium Act. This is the same organization, with the same funders, that ran the national anti-fracking and anti-nuclear campaigns. They pivoted to data centers as a strategic priority in 2025.

The Funding Network

FunderTypeRecipientsAmount
Columbus FoundationCommunity foundationFood & Water Watch$6.1M (2023)
Santa Barbara FoundationCommunity foundationFood & Water Watch$2.15M (2023)
Sea Change FoundationPass-through (Nat Simons)FWW, Sierra Club, LCV$23M from Bermuda-based Klein Ltd.
Open Society (Soros)Progressive philanthropyAI Now Institute toolkitsUndisclosed
Ford FoundationMajor philanthropyAI Now Institute toolkitsUndisclosed
Tides FoundationProgressive donor-advisedFood & Water Action Fund$50,000+
Advocacy Action FundPolitical fundFood & Water Action Fund$600,000
Hunt Oil family fortuneFamily wealthGuardrails Alliance (Super PAC)$5M+ initial
Hansjörg Wyss (Berger Action Fund)Swiss billionaireSixteen Thirty Fund / Arabella network$245M since 2016
Arabella / Vital Impact networkDark money pass-throughNew Venture Fund, Sixteen Thirty Fund, Windward Fund$500M+ foreign money (Americans for Public Trust)
Future Forward USA ActionPolitical dark moneyCourier Newsroom (16-state media network)$13.5M (2024)
ActBlueDemocratic fundraisingCourier Newsroom$2.5M (Dec 2025)

Sources: IRS Form 990 filings, InfluenceWatch, organizational annual reports. The major funders are the same foundations and donor networks that funded the anti-fracking, anti-pipeline, and anti-nuclear movements. The infrastructure (pass-through foundations, donor-advised funds, community foundations as intermediaries) is identical.

Key Players in the National Movement

Astroturf / Professional
Guardrails Alliance (Super PAC)

Co-founded by Leah Hunt-Hendrix, granddaughter of H.L. Hunt (Texas oil magnate), and Shaunna Thomas, career Democratic operative. $5M+ at launch, targeting $15M. Fossil fuel family money funding anti-tech activism through progressive political infrastructure.

Professional Advocacy
Honor the Earth

Co-founded by Winona LaDuke. Built data center tracker (160 sites), created "No Data Centers Toolkit." Same organization that fought Keystone XL and Line 3 pipeline, now redeploying the identical anti-infrastructure playbook against data centers. Frames them as "data colonialism."

Investigate Further
Party for Socialism & Liberation (PSL)

Marxist-Leninist organization organizing anti-data center campaigns in 14+ states. Linked to Neville Roy Singham ($285M through Goldman Sachs philanthropy fund, relocated to Shanghai). Connected to ~$23.6B in blocked investments. A small fraction of the overall movement, but present.

Professional Legal
Earthjustice + State Legal Orgs

Earthjustice, Midwest Environmental Advocates, and Southern Environmental Law Center provide the litigation infrastructure that local groups cannot afford. Professional attorneys filing multi-year lawsuits that delay projects indefinitely regardless of merit.

Astroturf Media
Courier Newsroom (16 states)

Founded by Democratic strategist Tara McGowan, incubated inside ACRONYM. Operates news outlets in 20+ states (The 'Gander in MI, UpNorthNews in WI, Copper Courier in AZ) that appear to be independent local journalism but are centrally coordinated. Published 242+ anti-data center media products across 16 states since 2025. Funded by Future Forward USA Action ($13.5M), ActBlue ($2.5M), Sixteen Thirty Fund ($260K). Was the third-highest spender on Meta political ads in October 2024, behind only Harris and Trump campaigns.

Dark Money Network
Arabella Advisors / Vital Impact

The Sixteen Thirty Fund (501(c)(4)) and New Venture Fund (501(c)(3)) are sister organizations administered by Arabella Advisors (rebranded as Vital Impact in Nov 2025). Swiss billionaire Hansjörg Wyss gave $245M since 2016. George Soros's Open Society gave $153.5M (2018-2022). New Venture Fund, Sierra Club Foundation, and Sixteen Thirty Fund collectively received $13M+ from pro-environmental donors. Americans for Public Trust documented $500M+ in foreign money flowing through this architecture. Power the Future has asked Congress to investigate.

Legitimate Research
Good Jobs First

25-year track record tracking corporate subsidies across ALL industries, not just data centers. Data-driven with bipartisan appeal (fiscal conservatives oppose corporate welfare too). Their subsidy research is legitimate and useful for designing better incentive policy.

Genuine Grassroots
Local Community Groups

Most local groups (No Data Center COS, Conserve Ohio, Great Lakes Neighbors United, Davie Against Data) are authentically resident-formed. But they are rapidly connected to FWW's coalition and provided professional toolkits, legal templates, media strategy, and funding pipelines within days of forming.

The anti-pipeline playbook, redeployed

The same people who fought Keystone XL and Dakota Access are now fighting data centers. Honor the Earth (now led by Krystal Two Bulls) transferred directly from pipeline activism to data center tracking, organizing with 15+ tribal nations and claiming victories including tribal bans and moratoria. Food & Water Watch pivoted from anti-fracking to anti-data center as a "strategic priority," coordinating a 230+ group moratorium letter to Congress in December 2025. Courier Newsroom published 242+ anti-data center media products across 16 states disguised as independent local journalism. The tactics are identical: community organizing toolkits, FOIA campaigns, regulatory delays, astroturf media amplification, and litigation through Earthjustice. A community group that forms on Monday can be filing FOIA requests and running media campaigns by Friday using these pre-built playbooks. The Soufan Center now monitors anti-data center sentiment as a security concern, noting a major surge beginning April 2026.

The honest assessment

Calling all opposition "astroturf" would be wrong. Many local concerns about noise, water, and electricity costs are legitimate. The 66% referendum win in Port Washington, WI demonstrates real community sentiment. But understanding who is funding, coordinating, and amplifying the movement matters for honest policy debate. When a $20M Washington D.C. advocacy organization distributes "How to Stop a Data Center Near You" toolkits to 520 groups across 48 states, a $13.5M-funded media operation publishes 242 anti-data center stories disguised as local journalism, and $500M+ in dark money flows through the Arabella/Vital Impact pass-through network from the same funders who bankrolled the anti-fracking campaigns, that is not spontaneous community organizing. It is a professional campaign using proven infrastructure from prior anti-infrastructure movements.

The right response is not to dismiss the concerns. It is to address them through policy (separate rate classes, water-free cooling mandates, noise setbacks, ratepayer protections) while understanding that the coordinating organizations have pre-existing political agendas that extend well beyond any single data center project.